ITEM: |
CONSENT
CALENDAR |
|
|||||
|
|
||||||
5. |
CONSIDER AUTHORIZATION TO
USE CONSERVATION CONTINGENCY TO FUND TEMPORARY EMPLOYEE IN WATER DEMAND
DIVISION RESULTING FROM WORKLOAD IMPACTS OF PROPOSED CALIFORNIA-AMERICAN
WATER MORATORIUM |
|
|||||
|
|
||||||
Meeting
Date: |
August 16, 2004 |
Budgeted: |
Yes |
|
|||
|
|
||||||
From: |
David A.
Berger, |
Program/ |
Conservation Contingency |
||||
|
General
Manager |
Line Item No.: |
$5,492 |
|
|||
|
|
|
|
||||
Prepared
By: |
Stephanie
Pintar |
Cost Estimate: |
N/A |
|
|||
General Counsel Approval: |
N/A |
|
|||||
Committee Recommendation: |
The Administrative Committee reviewed this item at its August 5, 2004 and recommended __________________. |
|
|||||
CEQA Compliance: |
N/A |
|
|||||
SUMMARY: The Board
will consider authorizing expenditures of up to $5,492 from the Conservation
Fund Reserve to contract for a temporary employee to assist the Water Demand
Division during the next 10 weeks to assist with an increased number of permit
applications and telephone calls. The
General Manager authorized hiring a contract employee to assist the division beginning
on August 2, 2004, using his authority to authorize expenditures of up to
$2,000. The request before the Board
is for an additional 396 hours at $13.87 per hour.
Water permit applications and related inquiries from the
public have increased over 100% during the past several weeks as a result of
California American Waters announcement of their pending application to the
Public Utilities Commission for a moratorium on new water connections. This extra demand upon Water Demand Division
staff time has resulted in a shift of priorities. The Conservation Representative II has shifted priorities from
returning telephone calls, responding to correspondence and meeting with
customers, to processing the increased number of permit applications. During the past seven work days (July
12-20), staff has processed 175 water permits, in comparison to 42 permits
processed during the same seven day time-frame in June 2004. The other Conservation Representatives are
responding to telephone calls when they are in the office and are delaying
follow-up on inspection violations and requests for water credits.
Impacts to customers include a significant increase in
waiting periods for inspections.
Currently staff is scheduling into the second week in August -- a
three-week delay. Additionally, a new
backlog of conservation enforcement letters has been created by the increased
telephone and walk-in traffic. The
longer the delay in enforcement, the more difficult it is to achieve the
desired compliance.
Hiring a temporary employee for approximately 10 weeks to
greet customers, answer the telephone and route calls, and to perform data
entry duties would allow Water Demand Division staff to devote their time and
attention to accomplishing technical duties and restore near-normal levels of
service.
It should be noted that in addition to the threat of a
moratorium, the Districts move to Stage 3 of the Expanded Water Conservation
and Standby Rationing Plan on June 22, 2004 has also impacted the workload of
the division. Currently, approximately
30 percent of the telephone calls received on a daily basis are related to
Cal-Am activities. Prior to Stage 3,
the Water Demand Division received few, if any, Cal-Am related telephone
calls. Since Stage 3 began, staff
estimates that the total average daily number of telephone calls is exceeding
110 calls per day. Prior to Stage 3,
the division received roughly 70 calls per day. In addition to customer service related to Stage 3, District
staff has committed to assisting Cal-Am with water audits and other duties related
to Stage 3, as schedules permit.
RECOMMENDATION: By adopting this item with the Consent Calendar, staff may extend the limited-term employment contract with an Office Assistant up to a maximum additional expenditure of $5,492. The extended contract will be for 396 hours at $13.87 per hour. The Administrative Committee considered this item at its August 5, 2004 meeting and recommended ..
IMPACT
ON STAFF AND RESOURCES: Funds totaling $5,500 are included in the Conservation portion of
the Personnel Contingency Fund. This fund is intended for use for unexpected
personnel expenses, such as the need for temporary help. It is listed under Personnel Costs in the FY
2004-2005 Budget. The cost of an office specialist would amount to
approximately $5,492.
BACKGROUND: Prompt customer
service is of prime importance to the Water Management District as a whole and
the Water Demand Division in particular.
The increase in workload caused by California-American Waters pending
moratorium has made it impossible for staff to maintain previous levels of
service, without temporary clerical assistance. The General Manager has
authorized up to $2,000 for this purpose.
However, Board approval is requested for funds sufficient to cover a longer
period of the time prior to the Public Utility Commission either granting or
denying a water connection moratorium. The limited-term employee will work in
the Water Demand Division and will be supervised by the Water Demand Manager.
U:\staff\word\committees\Admin\20040805\05\item5.doc